Solar-assisted compute for small LLM labs. What we have
checked, what we have not, and what comes next, in the open.
2 November 2026: Evidence sprint begins
We started a six-week evidence sprint, organised around Stage 1
of our proposed EDA flow: set energy,
latency, memory and accuracy targets from a measured system
baseline, using system models and workload traces. From today,
every change in the evidence is published on this page the same
day.
Two commitments frame the sprint:
- Simulation first, honestly labelled. Models
are published with their assumptions, so any reviewer can rerun
them and disagree with us precisely.
- Ten small-lab interviews. We are interviewing
ten independent builders and small LLM labs about compute access,
cloud cost, power reliability and data privacy. Interviews are
demand evidence and design input. Interviewees are not testers,
pilots or users, and we will not describe them that way.
2 November 2026: Energy model v1
Our first reproducible system model: an hourly, year-long
energy-budget simulation of one Combine node (PV array, battery
storage, inverter, one accelerator workstation), across 54
scenarios: three solar irradiation levels (4.0, 5.0 and
6.0 kWh/m2/day, following the bands in our NASA POWER based solar
atlas), three array sizes (2, 4 and 6 kWp), three storage sizes
(5, 10 and 15 kWh usable), and two scheduling strategies for
flexible fine-tuning work (a fixed evening start, versus
placement in the sunniest hours).
Workload assumption, stated plainly: one 4-hour
parameter-efficient fine-tuning session and 8 hours of local
inference per day, about 2,442 kWh of load per year. Workstation
power figures are assumptions based on a proposed 600 W class
accelerator, not measurements. Replacing them with measurements
is the next stage of this sprint.
What the model says:
- Sizing: at 5.0 kWh/m2/day, a 2 kWp array with
5 kWh of usable storage already covers about 99.9 percent of the
annual load on solar energy in the model. At 4 kWp, more than
40 percent of generated energy has no load to serve. For this
workload, a bigger array is wasted capital; growth should go
into more workload, not more panels.
- Scheduling: in the tightest case modelled
(4.0 kWh/m2/day, 2 kWp, 10 kWh storage), sun-aware placement
cuts grid import from 186 to 85 kWh per year, at the cost of
15 deferred fine-tuning sessions the single daily slot cannot
catch up. Scheduling trades grid energy for delay, and we
report both sides of that trade.
- Storage: moving from 5 to 15 kWh of battery
changes grid import only slightly in most scenarios, because
the load is daytime-heavy. Storage size should follow measured
evening demand, not intuition.
Update, same day: the cross-check below revises the sizing
headline to about 97 percent and withdraws the storage finding.
Next for the model: a cross-check against pvlib and the NREL
System Advisor Model, monthly seasonality from NASA POWER
climatology, and then measured workload traces in place of
assumed power figures.
2 November 2026: Model cross-check (Gate G1)
We checked energy model v1 against two validated open solar
models, pvlib and
the NREL System Advisor Model,
fed real hourly weather for three reference locations, one per
model scenario: Douala, Accra and Addis Ababa. They were chosen only
because their NASA POWER irradiation matches the scenarios. They are
reference points, not proposed sites. The code, the weather data
and every result are published
with this entry, so anyone can rerun it.
What we found:
- The two reference models agree within
2.5 percent, so the check itself is sound.
- Our v1 formula overstates solar yield by 3 to
9 percent on the same weather. It has no term for panel heat, and
at these tropical sites cells average 34 to 40 C in daylight,
costing 5 to 8 percent of output.
- The weather source matters more than the
formula. For the same locations, two satellite datasets
(NASA POWER and PVGIS SARAH2) differ by 7 to 20 percent in annual
irradiation. Sizing must be tested against both, not one.
What this changes in v1's findings, with real
seasons and the same annual energy:
- Sizing: the direction holds, the headline
does not. At 5.0 kWh/m2/day, a 2 kWp array with 5 kWh of storage
covers about 97 percent of the load, not 99.9 percent. The gap is
in the rainy months. A larger array still mostly produces surplus.
- Scheduling: holds, with a sharper trade. In
the tightest case, sun-aware placement cuts grid import from 286 to
107 kWh a year, but deferred sessions rise from 15 to 45, because
cloudy seasons last weeks.
- Storage: our earlier statement that battery
size is a weak lever does not hold in general. Away from the
lowest irradiation case, going from 5 to 15 kWh removes most of
the remaining seasonal grid import (75 to 29 kWh a year at the
Accra reference). We withdraw that finding.
Still open: every workstation power figure is an assumption. Next
are model v2 (hourly solar from pvlib, monthly seasons, both weather
sources) and then measured workload traces.
Full
method and results.